May 31, 2010 - working on cement pilings.

June 16, 2010 - Working on Footings

July 20, 2010 - Working on Footings

August 19, 2010 -Erecting structural steel on the East wall at the main entrance to the Multi-Plex

September 9, 2010 erection of pre-engineered steel building.

September 17, 2010 erection of pre-engineered steel building.

September 29, 2010 applying insulation.

November 3, 2010 walls - taken from highway.

Novemer 3, 2010 insulation and walls.

November 18, 2010 more walls and brick.

December 9, 2010 windows and more walls.

January 21, 2011 South West corner.
 Arena - Inside
 Arena - Inside

 Disability Lift

 Field House

 Fitness Centre

 Floor Sample

Ice Plant
Mezzanine
 Running Track

 Arena Cement/Ice Surface

 Arena Cement/Ice Surface

 Placing Coin & Town pins in cement/ice surface

 Coin & Town Pins in cement/ice surface

 
   
   
 
 
   
   

 

View All Events